Core Site Due Diligence Report

Fictional sample
Site Due Diligence Report
Juniper Commerce Center · Demonstration County, USA
Prepared for
Example Development Co.
01 · Executive summaryDecision-level findings, assumptions, and recommended actions
02 · Site and parcel overviewFictional parcel context, jurisdiction, and mapping notes
03 · Jurisdiction and zoningBase district, overlays, plan designation, and source links
04 · Proposed-use analysisPermission pathway, conditions, and confirmation items
05 · Development standardsSetbacks, height, intensity, and use-specific criteria
06 · Parking and landscapePlanning ratios, loading, buffering, and open questions
07 · Entitlement pathwayLikely applications, reviews, prerequisites, and decision bodies
08 · Risks and next stepsRisk matrix, open questions, source citations, and action plan

Illustrative structure only. Actual sections and depth depend on the property, proposed use, jurisdiction, available sources, and agreed scope.

Preliminary Fee Report

Fictional sample
Reviewing agencyFee categoryCalculation basisQuantity / unitEstimated lowEstimated highPayment timingSource dateSource citationAssumptionsVerification
Example Planning Dept.Site plan reviewBase + acreage8.4 acres$4,200$5,100At submittalMay 2026Sample Fee Schedule §4One review trackAgency confirmation needed
Example UtilityWater connectionMeter size2-inch meter$18,000$27,000Before permitJan. 2026Sample Utility Table 7Final demand unknownConcept-dependent
Example Building Dept.Plan reviewProject valuation$6.5M assumed$21,000$29,000At permit submittalMar. 2026Sample Valuation TableShell onlyValuation required

Preliminary planning-level estimates are based on publicly available fee schedules and stated project assumptions. Final fees remain subject to agency calculation, utility-provider confirmation, project valuation, and plan review.

Development Schedule

Fictional sample
Phase / duration
1
2
3
4
5
6
7
8
9
10
11
12
Due diligence · 3 wks
Applicant
Pre-application · 2 wks
Agency
Concept development · 4 wks
Applicant
Application / completeness · 4 wks
Agency
Completeness gate
Agency review · 8 wks
Agency →
Applicant-controlledMunicipality-controlledApproval gate / milestone

A full schedule may include due diligence, pre-application, concept development, entitlement preparation, submittal, completeness, agency review, resubmittals, a public hearing when required, approval, civil documents, building permit review, and construction start. It may also show dependencies and schedule risks. Depending on scope, delivery may be a PDF schedule, Excel schedule, Microsoft Project-compatible file, or visual Gantt chart. A native .mpp file is not promised.

Municipal Process and Application Matrix

Fictional sample
Required applicationReviewing agencySubmittal prerequisitesEstimated cyclesPublic hearingDecision authorityKey dependenciesOpen questions
Concept ReviewExample PlanningSketch plan; narrative1NoStaffApplicant conceptIs transportation memo required?
Conditional UseExample PlanningNeighborhood meeting; studies2–3YesPlanning CommissionComplete technical packageHearing cadence and noticing radius
Civil ConstructionExample EngineeringLand-use approval2–4NoCity EngineerUtility and drainage designOff-site improvement extent

Review cycles and timing are planning estimates, not agency commitments. Actual applications, prerequisites, authorities, and sequencing require property- and jurisdiction-specific confirmation.

Concept-Plan Compliance Review

Fictional sample
RequirementSample standardConcept indicationPreliminary statusFollow-up
Front setback25 ft minimum32 ft shownAppears consistentConfirm property line / ROW
Height45 ft maximum42 ftAppears consistentVerify rooftop screening rule
Parking1 / 350 sf118 spacesNeeds calculationConfirm net floor area
Landscape buffer15 ft east edge10 ft shownPotential conflictRevise concept or assess alternative
AccessAgency approvalTwo drivesUnverifiedCoordinate with roadway authority
Loading / coverage / open spaceMultiple standardsIncomplete conceptOpen itemProvide dimensions and calculations
Use-specific standardsScreening and operating criteriaNot yet documentedOpen itemConfirm operations and update plan notes

A concept review is a planning-level comparison of the materials provided against identified standards. It is not a survey, engineering design review, permit approval, or guarantee of compliance.

Selected for your scope:

Request a Scope and Fee

Formats that fit the team

Clear enough for the next conversation.

Actual deliverables may combine narrative, source links, tables, issue matrices, assumptions, visuals, and action items. Format and editability depend on the agreed scope.

No previews contain real client data, internal workbooks, confidential information, or proprietary analysis methods. Fictional values are examples, not pricing or schedule benchmarks for a real project.